ICS Weekly Report: July 3, 2020

Decorative image with colored diamonds on gray background
ICS Weekly Report: July 3, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, July 3, 2020

  • Xcel completed boring in the new primary feeder line.
  • Completed the structural steel platform in the Boiler Room.
  • Completed the concrete slab replacement in the Kitchen Area.
  • Completed the structural steel framing required for the all-glass partitions at the Media Center Break Out Rooms and Maker Space.
  • Completed in-wall rough-in and drywall hanging in the Resource Area.
  • Completed all classroom plumbing wall framing.
  • Started framing new metal stud partition walls in the Front Office.

Planned week ending Friday, July 10, 2020

  • Begin in-wall rough-in in the Media Center and Front Office area.
  • Complete roughing in at the Classroom Plumbing walls.
  • Begin hanging and taping drywall in the Classrooms at the plumbing walls.
  • Complete drywall taping in the Resource area and begin wall finishes.
  • Continue plumbing rough-in at the larger gang Restrooms.
  • Continue painting Corridor walls.

Middle School

Completed week ending Friday, July 3, 2020

  • Framing and in wall mechanical inspections throughout
  • Start drywalling framed walls throughout
  • Continued installation of unit ventilators

Planned week ending Friday, July 10, 2020

  • Continue unit ventilator installation
  • Continue drywall framing, start mudding and taping
  • HVAC ductwork installation on main level link
  • Install locker benches in pool area

Sheridan Hills Elementary

Completed week ending Friday, July 3, 2020

  • Continued above ceiling hydronic and domestic water piping in C wing.
  • Poured the Front Entry addition footings.
  • Completed all abatement scope.
  • Completed the demolition in the existing Front Office / future Media Center.
  • Completed demolition in the C wing stacked Restrooms.
  • Completed plumbing wall framing in the C wing Classrooms.
  • Continued underground plumbing rough-in throughout the building.

Planned week ending Friday, July 10, 2020

  • Complete flooring underlayment and continue plumbing rough-in in the C wing stacked Restrooms.
  • Begin insulating piping above ceiling in the Level 2 C wing Classrooms.
  • Complete Front Entry addition concrete foundation walls.
  • Complete framing metal stud partition walls in the new Front Office area.
  • Begin in-wall rough-in in the new Front Office area.
  • Complete the re-route of the existing fiber line into the building.

High School

Completed week ending Friday, July 3, 2020

  • Boiler Room
    • Mechanical connections to boilers
  • Area P Link
    • Wood blocking for windows and roof
    • Cabinet unit heater installation
  • Area D and E Bathrooms
    • Finished tile and plumbing fixtures
  • Lower Level Area F (Old locker rooms, new weight room)
    • Fill in walls for dance room
    • Painted walls and door frames
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough ins
    • Wall framing and drywall work
  • New Athletics Commons and concessions
    • Drywall framing and taping of walls and soffits
    • Plumbing rough ins in the concessions area
    • HVAC ductwork installation
  • New Athletic Corridor/Elevator
    • Waterproofing
    • Below grade masonry on east side
  • Main Gym
    • Finished abatement
  • Area A & B Art, FACS and Shop Classes
    • Epoxy floor patching
    • Mechanical and electrical rough ins
    • Wall framing
    • Ceiling grid and light installation
  • Loading Dock
    • Sewer repairs
    • Excavation
  • Exterior Work
    • Main entry irrigation

Planned week ending Friday, July 10, 2020

  • Boiler Room
    • Continue piping of boilers
  • Area P Link
    • Pour concrete floors
    • Window framing
  • Area D and E Bathrooms
    • Install toilet partitions
  • Lower Level Area F (Old locker rooms, new weight room)
    • Continue painting masonry walls
    • Flooring for weight room and dance room
    • Wall framing
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough ins
    • Wall framing and drywall work
    • Start casework
  • New Athletics Commons and concessions
    • Finish drywall and taping of walls and soffits
    • Paint walls and soffits
    • Fiberglass plastic wall finishes in concessions
    • Start wall and floor tile
  • New Athletic Corridor/Elevator
    • Waterproofing
    • Formed, rebar, poured east side footings
    • Above grade masonry on west side
  • Main Gym
    • Fin tube heat installation
    • Delivery of wood flooring
  • Area A & B Art, FACS and Shop Classes
    • Paint walls in Art Rooms
    • Fin tube radiation and diffuser installation
  • Loading Dock
    • Form footings and install rebar
  • Exterior Work
    • Soil corrections for new District Office Lot

STEM

Completed week ending Friday, July 3, 2020

  • Finished installing ceiling grid in the Special Education Suite
  • Installed lights, fire strobes, and speakers in Special Education Suite
  • Installed doors and interior window glazing in Special Education Suite
  • Drywall finishes in dishwasher area
  • Demolition in boiler room

Planned week ending Friday, July 10, 2020

  • Start installing casework in Special Ed., Pre-kindergarten and kindergarten classrooms
  • Start installing ceiling grid in lobby area
  • Start installing ceiling in kindergarten rooms
  • Start tiling dishwashing area
  • Above ceiling mechanical and electrical rough in in dishwashing area
  • Underground plumbing in boiler room
  • Set up concrete pours and infills for floors in boiler room
  • Install hot water heater in boiler room

Dual Language

Completed week ending Friday, July 3, 2020

  • Punch list items continue to be addressed.
  • Completed testing and balancing of the mechanical and HVAC systems.
  • Contractors worked to address action items on the Commissioning Corrective Action Log.

Planned week ending Friday, July 10, 2020

  • Continue to address punch list items.
  • ICS commissioning continued commissioning of the mechanical and HVAC systems.
  • Contractors to continue working to address action items on the Commissioning Corrective Action Log

Download the PDF report

Read More

Updated Bus Tracking App

If your child rides the school bus, and you previously used the Ride 360 app, we want you to know that the app is being replaced by a new, updated app called My Ride K-12. 

2023 graduate holding diploma

The Minnesota Department of Education released the 2023 graduation rates. We are excited to share that we have made consistent gains in many areas and that Richfield High School’s four-year graduation rate (94.1%) exceeds the statewide graduation rate of 83.3% by 10.8 percentage points.