Central Education Center

Completed week ending Friday, November 20, 2020

  • Presentation of construction plans took place at the school board meeting on Monday with approval to issue the plans for bidding.
  • Construction drawings were issued for bidding on Tuesday.
    • Bid date has been published as December 15th at 2:00

Planned week ending Friday, November 27, 2020

  • Continue bid solicitation to potential bidders, receive and review questions and format any clarifications for the upcoming addendum.
  • Pre-bid walkthrough is planned to take place on December 3rd at 3:00.

Richfield High School

Completed week ending Friday, November 20, 2020

  • Boiler Room
    • Commissioning, testing, and balancing
  • Area P Link
    • Waiting for windows and storefront door delivery
  • Lower Level Area F Dance Studio/Weight Room/Wrestling
    • Waiting for wall pad delivery
    • Dance room floor entrance ramp modifications.
  • Athletic Corridor
    • Fin tube covers installed

Planned week ending Friday, November 27, 2020

  • Boiler Room
    • Commissioning, testing, and balancing
  • Area P Link
    • Delivery of windows
  • Lower Level Area F Dance Studio/Weight Room/Wrestling
    • Interior glass installation
    • Finish dance room floor entrance ramp modifications.

Centennial Elementary

Completed week ending Friday, November 20, 2020

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.

Planned week ending Friday, November 27, 2020

  • Contractors to continue working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.

Sheridan Hills Elementary

Completed week ending Friday, November 20, 2020

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems.
  • Completed the above grade CMU, brick, and concrete chiller unit.
  • Completed the repairs of the deteriorated masonry louver well and backfilled the area.
  • Continued Lower Level mechanical piping.

Planned week ending Friday, November 27, 2020

  • Contractors to continue to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • Continued Lower Level mechanical piping.
  • Set the new chiller unit in the enclosure and begin making final mechanical and electrical connections.
  • Complete the remaining fence portions of the chiller enclosure walls.

Richfield Middle School

Completed week ending Friday, November 20, 2020

  • Phase 2 Area D Special Education/Link
    • Flooring throughout
    • Wall covering on ramp
  • Phase 2 New Conference Room and Staff Lounge
    • Waiting for casework delivery
  • Phase 2 FACS Lab
    • Installed ceiling grid
  • Phase 2 Chiller Tower
    • Continued chiller piping
  • Phase 3 Third Floor Restrooms
    • Finished tiling walls in south restrooms

Planned week ending Friday, November 27, 2020

  • Phase 2 Area D Special Education/Link
    • Restroom partitions and toilet accessory installation
  • Phase 2 New Conference Room and Staff Lounge
    • Flooring
  • Phase 2 FACS Lab
    • Install ceiling pad
  • Phase 2 Chiller Tower
    • Continue chiller piping
  • Phase 3 Third Floor Restrooms
    • Tile floors in south restrooms
    • Install grab bars and accessories in north restrooms

Richfield STEM Elementary

Completed week ending Friday, November 20, 2020

  • Continued testing, balancing, and commissioning of mechanical systems

Planned week ending Friday, November 27, 2020

  • Continue testing, balancing, and commissioning of mechanical systems

Richfield Dual Language School

Completed week ending Friday, November 20, 2020

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors worked to address issues identified during the 11-month warranty walkthrough.

Planned week ending Friday, November 27, 2020

  • Contractors to continue working to address items noted on the commissioning corrective action log.
  • Contractors to continue working to address issues identified during the 11-month warranty walkthrough.

Download a PDF of this report

First page of the PDF file: ISD280RichfieldICS_Weekly_Project_Update11-20-201

Read More

2023 graduate holding diploma

The Minnesota Department of Education released the 2023 graduation rates. We are excited to share that we have made consistent gains in many areas and that Richfield High School’s four-year graduation rate (94.1%) exceeds the statewide graduation rate of 83.3% by 10.8 percentage points. 

Empty Bowls Fundraiser: You're Invited

You’re invited to join us from 5-6:30 p.m. on Tuesday, March 12, for the Empty Bowls fundraiser. Empty Bowls is an event celebrating our community through art, music and food!